Capital Projects

Underground Piping Replacement

Scope: 

  • Includes underground hot and cold water pipe replacement in Music building, Robinson Hall, and Theater site.

Status:

  • Construction in progress

Schedule:

  • Design Completion - August 8, 2018
  • Construction Start - August 16, 2018
  • Construction Completion - January 21, 2019

Path of Travel

Project Photos

Underground Piping Replacement Project

CORE Building

 

Scope:

  • The CORE is a new 3 story building located at the northeast side of the campus, in close proximity to the Recreation and Wellness Center.

Status:

  • Currently in working drawing phase

Schedule:

  • Working drawings/permit application - now to Spring 2019
  • Construction start - Spring 2019
  • Construction completion - Spring 2021

Design Photos

CORE Building Project